At the February 17, 2021 meeting of the Executive Committee, the Committee considered the attached EX21-14 report from the Financial Strategy & Sustainability Division.

 

Ryan Johnson, Dale Schoffer and Mark Yemen, representing Buffalo Pound Water Treatment Plant, addressed the Committee.

 

The Committee adopted a resolution to concur in the recommendations contained in the report and that the $381 million debt amount noted under the “Impacts” section of the report be corrected and referenced as $362.4 million.

 

Recommendation #4 does not require City Council approval.

 