CONCLUSION
The 2015/2016 winter season can be described as well-below average, due to lower than average snow fall accumulations and warmer than average temperatures. This helped to achieve policy objectives 100 per cent of the time and lead to reduced winter activities that created a significant surplus. Any remaining funds at the end of the budget cycle will be transferred into the Winter Maintenance Reserve. Operationally, this made Winter Maintenance staff available to undertake tasks, typically performed by contracted services, to be done in-house, creating cost avoidance.
The Annual Winter Maintenance Summary 2015/2016 (Appendix A, attached) provides an overall summary of the winter maintenance activities for the 2015/2016 season. The following are highlights from that report:
· The 2015/2016 winter had well-below average conditions, due to a lack of snow and warmer temperatures;
· the policy objectives were met 100 per cent of the time;
· there was a surplus of $1.1 million at the end of 2015 and a similar surplus at the end of 2016 is anticipated;
· cost reductions and cost avoidance of approximately $717,000, were achieved through reallocation of winter staff reducing requirement for contracted services; and
· further enhancement of winter maintenance services are continually being examined and will be presented to City Council for approval in the future
BACKGROUND
On December 18, 2006, City Council (Council) approved the Winter Maintenance Policy, which was officially implemented in November 2007. Council approved the recommended policy amendments submitted in November 2010, December 2014 and December 2015. Annually, the delivery of winter maintenance services are evaluated against the objectives outlined in the Council approved Winter Maintenance Policy (Policy) with a commitment to continual improvement.
The purpose of the Winter Maintenance program is to provide winter maintenance activities that effectively supports the health, safety, attractiveness and economic viability of the city. The Policy was created in an effort to provide an acceptable and consistent level of service, when
maintaining the road network, and to ensure safe winter driving conditions for the citizens of Regina, including guidelines and timelines regarding the plowing of streets, sidewalks, and alleys following snow events, as well as for routine maintenance of the road network during the winter months. Within the Policy, there are several general objectives laid out to support the purpose of the program, which the branch strives to meet in both performance and end conditions. This report discusses the application of the Policy as it relates to operational, environmental and financial implications.
DISCUSSION
Appendix A of this report provides an overall summary of the 2015-2016 winter maintenance activities. The following are highlights of that report.
Below Average Winter
The winter season is defined as the period from October 1 to April 30. In general terms, and based on the five-year average, the 2015/2016 season can be described as well-below average with the following characteristics:
· Lower than average snow days
· Lower than average snow fall
· Above average temperatures
· Lower than average number of freeze/thaw cycles
Policy Objectives Met
Although several of the objective activities were not actioned due to the below average season, the review of documentation would indicate that the Policy’s quality objectives were met 100 per cent of the time.
Surplus
In 2015, Council approved an increase to the Winter Maintenance budget. This increase was used for the delivery of services to meet the level of service outlined in the Policy. The 2015 budget was $8.98 million and total expenditures were $7.8 million. At the end of 2015, there was a surplus of $1.1 million. The 2016 budget is $9.068 million, of which $2.707 million has been spent as of September 30. The total expenditures for 2016 are forecasted to be $5.645 million, based on average conditions expected for October through December. It is anticipated that there will be a similar surplus of approximately $1 million again at the end of 2016. The Winter Maintenance Reserve is in place to fund shortfalls as a result of extreme snow events or severe winter conditions. It has a current balance of $3.9 million and can hold a maximum balance of $3.923 million.
Cost Reductions and Cost Avoidance
In lieu of staffing complements and in an effort to maintain staffing levels necessary for storm and snow removal response, Winter Maintenance crews were allocated to other activities throughout the corporation, when winter maintenance activities were not required. A collaborative effort was made between departments, showcasing the mutual benefits for all parties. Winter Maintenance staff continues to investigate innovative solutions to reduce the cost
to deliver the policy objectives, as well as maximizing resources to perform work for other departments in delivering cost effective services in favour of contracted services. Operational support in the following areas achieved a combined cost savings of approximately $717,000:
· Asphalt Production and Materials Engineering
· Landfill Operations
· Water and Sewer Construction
· Sweeping and Alleys
· Concrete Services
· Asphalt Services
Future Changes
Further to the successes already achieved, additional proposed changes will be brought forward and are intended to enhance the City’s winter maintenance services:
· Snow Storage Site User Fee (approved by Council and ready for operation in the 216/2017 winter season)
· Enhanced Sidewalk Clearing
· Snow Routes Project
· Use of Liquid Salt in Ice Control
· Enhancement of Bicycle Lane Snow Clearing
RECOMMENDATION IMPLICATIONS
Financial Implications
None with respect to this report.
Environmental Implications
None with respect to this report.
Policy and/or Strategic Implications
Roadways & Transportation will continue to review the Policy to ensure that it aligns with Design Regina: The Official Community Plan, Bylaw No. 2013-48.
Other Implications
None with respect to this report.
Accessibility Implications
None with respect to this report.
COMMUNICATIONS
The Communications Department develops an annual strategy for winter operations and activities to inform the public. This strategy includes media relations, an advertising campaign for citizens to help clear snow from their sidewalks, as well as use of the City’s social media tools including Facebook, Twitter and YouTube. See Appendix A for more details.
DELEGATED AUTHORITY
A change to the Policy would require City Council’s approval. At this time, there are no policy changes proposed. As such, the disposition of this report is within the delegated authority of the committee.
Respectfully submitted, | Respectfully submitted, |
Norman Kyle, Director Roadways & Transportation | Karen Gasmo, Executive Director Transportation & Utilities |
Report prepared by: Chris Warren,
Manager, Winter Maintenance